Home/Guides/How to estimate concrete for a slab, step by step
Concrete & Masonry · 7 min read

How to estimate concrete for a slab, step by step

Measure, convert, add the right waste and order the right way. Here is the method estimators use to get slab volumes right the first time.

Running short on a pour is one of the most expensive mistakes on a small job. The truck has gone, the edge is starting to set, and you are mixing bags in a panic or booking a second delivery with a part-load charge on top. Over-ordering wastes money too, but much less of it. Estimating concrete well means measuring carefully, converting units without slips, and adding a waste allowance that fits the site.

1. Measure the real dimensions

Measure the inside of the formwork, not the drawing. Formwork is rarely set exactly to plan, and an extra 25 mm on each side of a large slab adds up. For irregular shapes, break the plan into rectangles, triangles and circles, work out each area, and add them together.

Thickness is where most errors creep in. A sub-base that dips by 10–15 mm across a large area can add several percent to the volume. Use a string line or laser and check the depth from the top of the forms down to the sub-base at several points. Use the average, not the design figure.

2. Convert everything to one unit

In the UK, the trap is mixing metres and millimetres. A 6 × 4 m slab that is 100 mm thick is 6 × 4 × 0.1 = 2.4 m³. Always turn the thickness into metres before you multiply.

Formula: volume = length × width × thickness, with every dimension in the same unit.

3. Add a waste allowance

Concrete gets lost to uneven sub-bases, slight form bulges, spillage, what's left in the pump line or barrow, and the bit you can't get out of the drum. Typical allowances:

SituationAllowance
Formed slab on a well-compacted, level base5%
Typical residential slab or patio8–10%
Hand-dug trenches, uneven ground, pumped pours10–15%

4. Decide how to supply it

Below about 1 m³, pre-mixed bags are usually simplest. Above that, ready-mix or a mix-on-site truck is normally cheaper and far less work. Our bags vs ready-mix guide covers the break-even point in detail.

Ready-mix is usually ordered in 0.25 m³ or 0.5 m³ steps, so round up. Ask about part-load charges below 3–4 m³, and about minimum orders from volumetric (mix-on-site) lorries.

5. Don't forget reinforcement and extras

The concrete line is only part of the takeoff. A complete slab estimate usually includes:

  • MOT Type 1 sub-base, compacted in layers
  • Vapour barrier or DPM where the slab is inside a building
  • Steel mesh (A142 or A193) or rebar, plus chairs or spacers
  • Edge forms, stakes, expansion joint strip and curing compound
  • Pump hire if the truck can't reach

A worked example

A 7 × 5 m garage slab at 125 mm: 7 × 5 × 0.125 = 4.375 m³. Add 8% waste for 4.73 m³, then order 4.75 m³.

The concrete slab calculator does all of this for you. It shows the ready-mix order, every bag size and a site-mix recipe side by side, and drops the materials straight into a job.

This guide is general information for estimating. It is not engineering, legal or tax advice. Check the Building Regulations and Building Control for your project.